Pomerado Elementary School
Prop C Construction Start Date : June 2008
Prop C Estimated Completion Date: May 2009
Prop C Estimated Completion Date: May 2009
Pomerado Elementary School was built in 1960.
The Principal: Lisa Danzer
Projects planned at Pomerado include:
The Principal: Lisa Danzer
Projects planned at Pomerado include:
- Utility upgrade/efficiency improvements
- Renovate/upgrade restrooms as needed
- Modify/expand/renovate library
- Modernize classrooms, such as lighting, power/data, flooring, and marker boards
- Renovate/expand staff work area
- Add/renovate computer laboratory
- ADA upgrades/compliance
- Food service area expansion/renovation, including new covered lunch area
- Site/playground improvements for code and safety compliance
- Add/upgrade furniture and instructional equipment
- Upgrade/replace communications and fire alarm systems
Accomplished in July 2008
- Poured concrete footings and concrete walls.
- Cure the concrete.
- Backfill and waterproof the back wall.
Planned for August 2008
- Pour the concrete walkway/ramp.
- Install all the railings.
- Complete the conduits and install new lightpoles.
- Clean up, punchlist and demobilization.