Building for Success » Proposition C Timeline

Proposition C Timeline

Proposition C Timeline

Current Building for Success Timeline (last updated 2010)

The following timeline has been established to guide program progress. Any program of this magnitude is subject to changes.

The timeline will continue to be updated as the program continues.
 
 School Site    Estimated/Actual
 Construction Start
   Estimated/Actual
 Completion Date
 Abraxas High School    March  2008    September  2008 Completed
 Bernardo Heights Middle     May  2010    February  2011  
 Black Mountain Middle     June  2008    June  2009 Completed
 Canyon View Elementary     June  2009   August  2009 Completed
 Chaparral Elementary     April  2008   August  2008 Completed
 Deer Canyon Elementary     June  2009   August  2009 Completed
 Meadowbrook Middle     June  2008    January  2009 Completed
 Morning Creek Elementary     June  2010   December  2010  
 Mt. Carmel High  Phase IV    June  2009   August  2010  
 Pomerado Elementary     November  2008    August  2009 Completed
 Poway High Phase IV    October  2009    March  2010 Completed
 Rancho Bernardo High Phase II    September  2010    December  2010  
 Rolling Hills Elementary     May  2008    March  2009 Completed
 Sundance Elementary     May  2009    August  2009 Completed
 Sunset Hills Elementary     April  2009    August  2009 Completed
Tierra Bonita Elementary     June  2010    August  2010  
 Turtleback Elementary     June  2009    August  2009 Completed
Valley Elementary     April  2008    January  2009 Completed